As of July 26th, we now have about 80% completion on the
new run. All the major dirt moving have been finished, we are just
touching up the edges. The T-bar is now completely taken down. The
top shack has been removed as well as the deck. The bottom shack has been
removed and is being prepared to be taken to the top for the return station
shack for the new chair. The new shack for the bottom of the chair is
being built to be moved in when needed.
The first semi load of parts for the chair have arrived.
On it included bolt cages for the tower foundations, crossarms for the chair,
and some little parts for here and there. All the foundations for the
towers have been dug, and the rebar and bolt cages are in place. Tower 6
and 7's concrete has been poured and plans for more concrete to be poured for
this week sometime are in order.
Here are some more pictures for you to see.
|
|
|
|
|
|
|
First Semi Load Of New Chair Parts |
|
|
|
|
|
|
|
|
|
|
|
|
|
Top Of T-Bar Before Dismantling |
|
|
|
|
|
|
|
|
|
|
|
|
|
Top Of T-Bar After Dismantling |
|
|
|
|
|
|
|
|
|
|
|
|
|
Our Tower Garden, Soon They Will Grow To Be Full Size! |
|
|
|
|
|
|
|
|
|
|
|
|
Foundation For Return Station |
|
|
|
|
|
|
|
|
|
|
|
|
New Run From The Top (Before) |
|
|
|
|
|
|
|
|
|
|
|
|
New Run Top Pitch From Below |
|
|
|
|
|
|
|
|
|
|
|
|
|
New Run From The Top (After) |
|
|
|
|
|
|
|
|
|
|
|
|
Floor Of Bottom Shack For New Chair |
|
|
|
|
|
|
|
|
|
|
|
|
Bottom Shack With Walls Partially Up |
|
|
|
|
|
|
|
|
|
|
|
|
First Load Of Concrete For Tower 7 Foundation |
|
|
|
|
|
|
|
|
|
|
|
|
|
First Concrete Pour Started |
|
|
|
|
|
|
|
|
|
|
|
|
Return Station Foundation |
|
|
|
|
|
|
|
|
|
|
|
|
|
Moving Bottom T-Bar Shack Out Of The Way |
|
|
|
|
|
|
|
|
|
|
|
|
Tower 7 Foundation Finished Product |
|
|
|
|
|
|
|
|
|
|
|
|
Bottom Of T-Bar (Before Tree Replant) |
|
|
|
|
|
|
|
|
|
|
|
|
Bottom Of T-Bar (After Trees Removed For Replant) |
|
|
|
|
|
|
|
|
|
As of July 6th, the cable is off of the t-bar and most of
the towers have been removed. The bullwheel shack at the bottom has also
been removed and bottom shack was stripped of all the electrical. Leitner
Poma is on site and will have more crew arriving this week to start digging
foundations for the towers on the new chair. Also if plans proceed and the
weather cooperates, dirt work on the new run should start next week.
Here are some pictures of the brush cutter this spring and
the t-bar being stripped.
Keep checking back, we'll try and keep you as updated as
we can.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bottom t-bar shack all empty |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Stipped of the bullwheel shack |
|
|
|
|
|
|
|
|
|
|
|
|